Project
Share the project

Peribonka Hydroelectric Power Plant | 405 MW

  • Construction of a temporary diversion.
  • Excavation of the access tunnel - Phase 1.
  • Excavation and concreting of the powerhouse and spillway concrete works.
  • The Peribonka power plant is equipped with 3 Francis units.

Features

  • Activity Sector Energy
  • Client Hydro-Québec
  • Year 2004-2007
  • Value $100,000,000
  • Engineers Tecsult inc.
  • Other Stakeholders Neilson Inc.
Place