  • Construction of a rock-filled dam at the head of Long Lake hydroelectric project which can hold up to 30 million cubic meters of water.
  • Construction of the intake, the spillway, the widening of an existing 68 m tunnel, 7 km of penstock 1.35 m Ø.
  • Construction of a power station for the 2 Pelton turbines and 10 km of 138 KV transmission line.

Features

  • Activity Sector Energy
  • Client Regional Power
  • Year 2011-2013
  • Value $77,000,000
  • Other Stakeholders Neilson Inc / WVCC